Announcement of Ministry of Construction of the People's Republic of China
Foreword
1 General Provisions
2 Terms
3 Transportation,Storage and Keeping of the Cables and Accessories
4 Construction of the Attached Facilities and Structures of Power Cable Line
4.1 Processing and Laying of Cable Duct
4.2 Fabrication and Installation of the Cable Rack
4.3 Construction of Other Protection Facilities and Structures
5 Laying of Cables
5.1 General Requirements
5.2 Laying of the Direct Buried Cable
5.3 Laying of the Cable in the Cable Ducts
5.4 Laying of the Cable in the Cable Structures
5.5 Laying of the Cable on Bridge
5.6 Laying of the Submarine Cable
5.7 Laying of the Overhead Cable
6 Installation of the Cable Accessories
6.1 General Requirements and Preparation Work
6.2 Installation Requirements
7 Construction of the Fireproofing and Flame-retardant Facilities in the Power Cable Line
8 Transfer and Acceptance
Appendix A Common Calculation Equations for Lateral Pressure and Traction Force
Explanation of Wording in This Code