9.6 Sealing Chute

Ⅰ Major Items

9.6.1 Countersunk screws fixing the sealing chute shall be lower than sliding surface of the chute.

Quantity checked:All.

Checking method:Check by observation.

9.6.2 Reserved gaps of respective parts in sealing chute for thermal expansion shall meet the requirements of design technical documents.

Quantity checked:All.

Checking method:Check installation quality records or by field tests.

Ⅱ General Item

9.6.3 Allowable deviation of sealing chute installation shall be in accordance with those specified in Table 9.6.3.Refer to Figure 9.6.3.

Quantity checked:All.

Checking method:Refer to 9.6.3.

Table 9.6.3 Allowable deviation of sealing chute installation(mm)

img
img

Figure 9.6.3 Elevation measurement of sealing chute

1-Pallet rail;2-Sealing chute;3-Longitudinal center line of traveling grate equipment;4-Special sample rod for rail