3 Equipment Foundation,Anchor Bolt and Base Plate
3.1 General Requirement
3.1.1 This chapter is applicable to the installation quality acceptance of mineral processing equipment foundation,anchor bolt and base plate.
3.1.2 Before equipment installation,equipment foundation acceptance inspectionmust be made,and equipment shall not be installed if the foundation fails to pass the required quality acceptance inspection.
3.1.3 Settlement observation shall be carried out for the foundation of the main mineral processing equipment and records shall be made.