GB50402-2007烧结机械设备工程安装验收规范(英文版)
上QQ阅读APP看本书,新人免费读10天
设备和账号都新为新人

6.11 Head Bending Rail and Intermediate Rail

Ⅰ Dominant Item

6.11.1 Preset thermal expansion gap for rail joints must meet requirements of design technical document.

Check quantity:to check all.

Inspection method:to check installation.

Ⅱ General Item

6.11.2 Installation for head bending rail shall take chain blade of head wheel as reference;tolerance for installation of the bending rail shall meet requirements in Table 6.11.2,see Figure 6.11.2.

Check quantity:to check all.

Inspection method:see Table 6.11.2.

Table 6.11.2 Tolerance for installation of head bending rail

img
img

Figure 6.11.2 Head bending rail

1-Chain wheel;2-Head bending rail;3-Longitudinal centerline of sintering equipment

6.11.3 Tolerance for intermediate rail shall meet requirements in Table 6.11.3.

Check quantity:to check all.

Inspection method:see Table 6.11.3.

Table 6.11.3 Tolerance for installation of intermediate rail

img