6 Strip Connection Equipment

6.1 Installation of Stitcher

6.1.1 When adjusting the elevation,the surface of sewing table of strip should be taken as the datum point.

6.1.2 When adjusting the elevation of pressing device of inlet and outlet,the fixed roll should be taken as the datum point.

6.1.3 When adjusting the levelness,the surface of guide plate table of strip should be taken as the datum point.