Azure DevOps Server 2019 Cookbook(Second Edition)
上QQ阅读APP看书,第一时间看更新

How it works...

When you hover over a task of interest, the drop plan will render dependency links out to tasks that are related to the task you have selected, in addition to the product backlog item all the tasks are linked to. In this case, you now know that the product backlog item has three key tasks in flight, one of which is only likely to complete on the last day of the sprint. This gives you an opportunity to discuss the order in which the tasks are scheduled. For example, in this case, if you think the task scheduled for the last day of the sprint has more value, it should be brought forward in place of something else. In addition to this, the extension allows you to visualize an individual's and team's days off, as well as blocked tasks: