5 Overall Installation of the Machine Train

5.1 Installation of Supporting Plates and Shims

5.1.1 Jackscrew supporting plate shall be set up in accordance with the following requirements:

a)Mark out the position of jackscrew supporting plate on the equipment foundation and chisel the foundation pit slightly bigger than outline dimensions of the plate,as shown in Figure 5.1.1;

b)Adjust the jackscrew supporting plate with 5mm/m levelness and±2mm allowable deviation of the elevation and meet the normal adjusting requirement of the equipment jackscrew;

c)Set up formwork and grout with non-shrinkage grouting materials.The height of grouting layer shall be 3mm-5mm lower than the upper surface of jackscrew supporting plate.

img

Figure 5.1.1 Installation of supporting plate

1-Foundation;2-Supporting plate;3-Cement mortar bedding cushion

5.1.2 Shims shall be set up in accordance with the following requirements:

a)Keep the thickness of the machine foundation grouting layer between 20mm-40mm,chisel out shims position on the both sides of anchor bolts with 5mm/m allowable deviation of the levelness and then set up formal shims;

b)If the thickness of the foundation grouting layer exceeds 40mm,the setup of shims shall comply with the requirements of Article 5.1.1.